A faster exact method for solving the robust multi-mode resource-constrained project scheduling problem

Optimization and Control 2022-03-15 v1 Discrete Mathematics

Abstract

This paper presents a mixed-integer linear programming formulation for the multi-mode resource-constrained project scheduling problem with uncertain activity durations. We consider a two-stage robust optimisation approach and find solutions that minimise the worst-case project makespan, whilst assuming that activity durations lie in a budgeted uncertainty set. Computational experiments show that this easy-to-implement formulation is many times faster than the current state-of-the-art solution approach for this problem, whilst solving over 40% more instances to optimality over the same benchmarking set.

Keywords

Cite

@article{arxiv.2203.06983,
  title  = {A faster exact method for solving the robust multi-mode resource-constrained project scheduling problem},
  author = {Matthew Bold and Marc Goerigk},
  journal= {arXiv preprint arXiv:2203.06983},
  year   = {2022}
}

Comments

14 pages, 4 figures. In submission at Operations Research Letters