Budget Minimization is a scheduling problem with precedence constraints, i.e., a scheduling problem on a partially ordered set of jobs $(N, \unlhd)$. A job $j \in N$ is available for scheduling, if all jobs $i \in N$ with $i \unlhd j$ are…
Weighted flow time is a fundamental and very well-studied objective function in scheduling. In this paper, we study the setting of a single machine with preemptions. The input consists of a set of jobs, characterized by their processing…
We consider the $1||\sum w_J U_j$ problem, the problem of minimizing the weighted number of tardy jobs on a single machine. This problem is one of the most basic and fundamental problems in scheduling theory, with several different…
This article studies the problem of modifying the action ordering of a plan in order to optimise the plan according to various criteria. One of these criteria is to make a plan less constrained and the other is to minimize its parallel…
We consider several combinatorial optimization problems which combine the classic shop scheduling problems, namely open shop scheduling or job shop scheduling, and the shortest path problem. The objective of the obtained problem is to…
The NP-hard scheduling problem P||C_max encompasses a set of tasks with known execution time which must be mapped to a set of identical machines such that the overall completion time is minimized. In this work, we improve existing…
This paper addresses the scheduling problem of minimizing the total weighted tardiness on a single machine with step-deteriorating jobs. With the assumption of deterioration, the job processing times are modeled by step functions of job…
We study the problem of scheduling maintenance on arcs of a capacitated network so as to maximize the total flow from a source node to a sink node over a set of time periods. Maintenance on an arc shuts down the arc for the duration of the…
In this work, we study a single-machine scheduling problem that aims at minimizing the total cost of a schedule subject to start-time dependent costs. This framework naturally captures scenarios where costs fluctuate throughout the day,…
Since its development in the early 90's, parameterized complexity has been widely used to analyze the tractability of many NP-hard combinatorial optimization problems with respect to various types of problem parameters. While the generic…
In the paper we consider the problem of scheduling $n$ identical jobs on 4 uniform machines with speeds $s_1 \geq s_2 \geq s_3 \geq s_4,$ respectively. Our aim is to find a schedule with a minimum possible length. We assume that jobs are…
In this paper we investigate the workflow scheduling problem, a known NP-hard class of scheduling problems. We derive problem instances from an industrial use case and compare against several quantum, classical, and hybrid quantum-classical…
We study a natural variant of scheduling that we call \emph{partial scheduling}: In this variant an instance of a scheduling problem along with an integer $k$ is given and one seeks an optimal schedule where not all, but only $k$ jobs, have…
This paper explores fast, polynomial time heuristic approximate solutions to the NP-hard problem of scheduling jobs on N identical machines. The jobs are independent and are allowed to be stopped and restarted on another machine at a later…
This paper considers single-machine scheduling problems in which a given solution, i.e. an ordered set of jobs, has to be improved as much as possible by re-sequencing the jobs. The need for rescheduling may arise in different contexts,…
We consider the offline sorting buffer problem. The input is a sequence of items of different types. All items must be processed one by one by a server. The server is equipped with a random-access buffer of limited capacity which can be…
Generalizing many well-known and natural scheduling problems, scheduling with job-specific cost functions has gained a lot of attention recently. In this setting, each job incurs a cost depending on its completion time, given by a private…
Speed-robust scheduling is the following two-stage problem of scheduling $n$ jobs on $m$ uniformly related machines. In the first stage, the algorithm receives the value of $m$ and the processing times of $n$ jobs; it has to partition the…
We study shared processor scheduling of $\textit{multiprocessor}$ weighted jobs where each job can be executed on its private processor and simultaneously on possibly $\textit{many}$ processors shared by all jobs in order to reduce their…
We consider scheduling problems for unit jobs with release times, where the number or size of the gaps in the schedule is taken into consideration, either in the objective function or as a constraint. Except for a few papers on energy…