Related papers: Project-X: A new high intensity proton accelerator…
One of the fundamental challenges for future leptonic colliders and neutrino factories as well as for high-sensitivity studies of lepton universality is to design and construct new high-intensity sources of muons and positrons. The…
The Long Baseline Neutrino Experiment (LBNE) will utilize a neutrino beamline facility located at Fermilab. The facility is designed to aim a beam of neutrinos toward a detector placed in South Dakota. The neutrinos are produced in a…
Fermilab is developing a Proton Improvement Plan (PIP) to increase throughput of its proton source. The plan addresses hardware modifications to increase repetition rate and improve beam loss while ensuring viable operation of the proton…
Fermilab is upgrading its Booster synchrotron to increase ramp rate and intensity. This is part of the Proton Improvement Plan (PIP-II) that will allow the Main Injector to achieve proton beam power of 1.2 MW within the next few years. This…
The Long Baseline Neutrino Experiment (LBNE) will utilize a neutrino beamline facility located at Fermilab to carry out a compelling research program in neutrino physics. The facility will aim a beam of neutrinos toward a detector placed at…
Searches for dark-matter particles at the GeV mass scale has been receiving much attention in the last several years, partly motivated by the failure of direct and indirect searches of heavier candidates to produce a signal. The SpinQuest…
The bulk irradiation of materials with 10-30 MeV protons promises to advance the study of radiation damage for fission and fusion power plants. Intermediate energy proton beams can now be dedicated to materials irradiation within…
Fermilab operates the world's most intense antiproton source. Recently proposed experiments can use those antiprotons either parasitically during Tevatron Collider running or after the Tevatron Collider finishes in about 2011. For example,…
The upcoming long baseline neutrino experiments aim to enhance proton beam power to multi-MW scale and utilize large-scale detectors to address the challenge of limited event statistics. The DUNE experiment at LBNF will test the three…
Fermilab operates the world's most intense antiproton source. Newly proposed experiments can use those antiprotons either parasitically during Tevatron Collider running or after the Tevatron Collider finishes. For example, the annihilation…
The Fermilab booster has an intensity upgrade plan called the Proton Improvement plan (PIP). The flux throughput goal is 2E17 protons/hour, which is almost double the current operation at 1.1E17 protons/hour. The beam loss in the machine is…
We have measured cross sections for forward neutron production from a variety of targets using proton beams from the Fermilab Main Injector. Measurements were performed for proton beam momenta of 58 GeV/c, 84 GeV/c, and 120 GeV/c. The cross…
Fermilab operates the world's most intense antiproton source. Newly proposed experiments can use those antiprotons either parasitically during Tevatron Collider running or after the Tevatron Collider finishes in about 2010. In particular,…
Proton beam dumps are prolific sources of mesons enabling a powerful technique to search for vector mediator coupling of dark matter to neutral pion and higher mass meson decays. By the end of the decade the PIP-II linac will be delivering…
The Fermilab High Intensity Neutrino Source program has built and commissioned a pulsed 325 MHz RFQ. The RFQ has successfully accelerated a proton beam at the RFQ design RF power. Experiences encountered during RFQ conditioning, including…
We carry out a state-of-the-art assessment of long baseline neutrino oscillation experiments with wide band beams. We describe the feasibility of an experimental program using existing high energy accelerator facilities, a new intense wide…
The Proton Improvement Plan, Stage Two (PIP-II) is a program of upgrades proposed for the Fermilab injection complex, which central part is an 800 MeV, 2 mA CW SRF linac. A prototype of the PIP-II linac front end called PIP-II Injector Test…
An overview is presented of the upgrade of JLab's cw electron accelerator from a maximum beam energy of currently 6 GeV to 12 GeV. Construction of the 12 GeV upgrade project has started in 2008. A broad experimental program has been…
The Neutrinos at the Main Injector (NuMI) facility at Fermilab began operations in late 2004. NuMI will deliver an intense muon neutrino beam of variable energy (2-20 GeV). Several aspects of the design and results from runs of the MINOS…
The Minos+ experiment is an extension of the Minos experiment at a higher energy and more intense neutrino beam, with the data collection having begun in the fall of 2013. The neutrino beam is provided by the Neutrinos from the Main…