Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques

Risk Management 2024-06-06 v1

Abstract

The aim of this paper is to describe a new an integrated methodology for project control under uncertainty. This proposal is based on Earned Value Methodology and risk analysis and presents several refinements to previous methodologies. More specifically, the approach uses extensive Monte Carlo simulation to obtain information about the expected behavior of the project. This dataset is exploited in several ways using different statistical learning methodologies in a structured fashion. Initially, simulations are used to detect if project deviations are a consequence of the expected variability using Anomaly Detection algorithms. If the project follows this expected variability, probabilities of success in cost and time and expected cost and total duration of the project can be estimated using classification and regression approaches.

Keywords

Cite

@article{arxiv.2406.02589,
  title  = {Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques},
  author = {Fernando Acebes and M Pereda and David Poza and Javier Pajares and Jose M Galan},
  journal= {arXiv preprint arXiv:2406.02589},
  year   = {2024}
}

Comments

20 pages

R2 v1 2026-06-28T16:53:24.151Z